Technical corner · Automation · 6 min read
Spare parts no longer available, software that only runs on an old PC, nobody who really knows the program: many plants live with end-of-life PLCs. As long as the machine runs, the decision is postponed. Until the day a card fails and the stop lasts days instead of hours.
Replacing a PLC is not just a hardware swap. Well prepared, it is also an opportunity to make the machine more reliable and easier to troubleshoot. Here are the 5 steps of a successful migration.
1. Survey the existing installation
Gather everything that exists: program backup, electrical diagrams (often out of date), list of inputs and outputs, links with neighbouring machines. This is also the time to note known problems and the teams’ requests.
2. Write the functional analysis
This is the most often neglected step, and the most profitable. It describes what the machine must do: sequences, operating modes, safety functions, faults. Validated with production and maintenance, it becomes the reference for programming and testing.
3. Choose the hardware and prepare
The choice depends on the size of the machine and the existing installed base: for example a Siemens S7-1200 G2 for a compact machine, an S7-1500 for a more complex line. The new electrical diagram and the operator panel are prepared, and the program is tested in the office, in simulation, before going on site.
Automatically converting the old program looks faster. But it keeps the original flaws and a structure that is hard to read. Starting again from the functional analysis gives a clear, documented program with a real diagnostic screen.
4. Plan the changeover
Everything that can be prepared in advance should be: cabinet or panel pre-wired, terminals labelled, communication with neighbouring machines tested. The on-site changeover then becomes a short, controlled stop rather than an adventure.
5. Commission and document
Function-by-function tests, tuning, training of operators and technicians, then handover of up-to-date documentation: diagrams, status manual, program backup. This is what will allow fast troubleshooting in the years that follow.
A real example
On the Biko unwinder at Elis Belgium, ITS replaced the B&R PLC with a Siemens S7-1200 G2, rewrote the program from a functional analysis, installed a new diagnostic panel and delivered complete EPLAN electrical diagrams. Commissioning: 3 days.
To go further on diagnosis, read also: Machine breakdowns: cut diagnostic time.
An end-of-life PLC on one of your machines? Let’s talk before it breaks down.